Coating Area is in Preparation for Start-Up

04.09.2013

In August 2013, installation of equipment in the coating area, considered as one of the most important facilities built under the Big Koryazhma project, was completed. Currently, commissioning is under way in the area, including testing of electric motors, adjustment of the coater control software, preparation for commissioning trials of the winder, and work at the roll handling equipment.

Installation of equipment in the Coating Kitchen is nearing completion.

Outside the coating area, site improvement is in full swing, with access ways to the coating area and PM7 being built, pedestrian area being created, and landscaping work being performed.