Paul Herbert Reviews Progress at Big Bratsk Construction Sites

22.07.2011

On July 22 Paul Herbert, Ilim Group's CEO, visited the Big Bratsk construction sites. He was generally satisfied with the construction progress.

Mr. Herbert and his management team visited the Chlorine Dioxide Plant site with a warehouse and an oxygen plant, Wood Port and woodyard construction site. Top management also went to the wastewater treatment plant where a foundation for a local wastewater treatment facility is being built. The visit was completed by inspection of the fiberline, new recovery boiler, sludge dewatering area, caustic plant and additional rail tracks.

Once the construction site was inspected, Paul Herbert held a meeting with the project managers. He commented on schedule delays at certain facilities but was generally satisfied with the progress.