Rebuild Starts at Pulp Line 2 to Accommodate Future Volumes of Big Bratsk

11.11.2011

Ilim Group's Bratsk Mill has launched a large-scale project aimed to rebuild the finished goods warehouse at Pulp Line 2. The project to be implemented during three years involves a large work scope in different areas, including electric power supply, heating, fire alarm, smoke removal, ventilation and rainwater drainage. Total installed cost is about RUB 150 million. The start-up of the Big Bratsk will boost market products output which will require a warehousing capacity to accommodate at least a one-day inventory. Current capacity is limited to 16 batches per day. The start-up of new capacities is expected to drive the warehousing performance to 40 - 50 batches. Warehousing space is planned to be expanded through dismantling of old production lines and rooms.