Construction Chronicles

22.01.2012

Installation workers are assembling the framework of the building that will house the paper machine. Floor concreting is ongoing in the finishing building. Contractor is expected to concrete an area of 20,000 sq. m under a very tight schedule of approximately two months. 16,000 sq. m of concreting is already done with "not such a huge" area waiting to be concreted.