Big Koryazhma

Coater is 92% Complete

25.07.2013
The coater, which is being built under the Big Koryazhma project, is now 92% complete. PM7 is 100% complete. As a reminder, on March 3, 2013 PM7 produced its first paper.
Mechanical installation is 99% complete, installation of electrical equipment, instrumentation and automation devices is 86% complete. Construction work under the project is 92% complete. Landscaping of the Mill's site is underway and will be followed by completion of the commissioning stage.