Less Than One Month Till PM Start-Up

29.11.2012

Just one month is left until PM7 is put into operation. Currently, press, drying and wire section equipment of PM7 is being installed. Installation of steam condensate and heat recovery systems is in full swing. Office and utility rooms, as well as control rooms are being fit out with necessary equipment. Pumping system is currently being installed at ground level.

Commissioning of the load-center substation, which ensures power supply for the new mill is under way.

Steel structures for the coater have been erected and currently sandwich panels are being installed at some parts of the coater.

Testings are currently being performed in the finishing building.

In November 2012 railway line was built at PM7 area to supply raw materials to the respective production site.