Big Bratsk

Big Bratsk. Digester Work is Nearing Completion

19.03.2012

Construction work at the digester is nearing completion.  On March 19, the last 22nd shell of the digester was installed.  The only part left to be erected on the digester is a top separator consisting of a separator body, screw conveyor and screens.  Total weight of this part is 45 tons.  Digester's height is 60 meters.  Building frame is fully completed, elevation 10 and its foundations were installed.  Installation of elevation 20 is 60% complete, foundations are partially completed, and equipment is partially installed.  Two contractors are working on site.  Equipment installation in the digester building is 50% complete.